Blog Topic
Mechanics Liens, Stop Notices and Payment Bonds
I Forgot To File A Legal Action to Foreclose
On My Mechanics Lien Within 90 days: Now What?
Or
My Contractor Recorded A Mechanic's Lien and not Filed A Timely Lawsuit to Foreclose On It: Now What?
By
William C Last, Jr.
Attorney at Law
??
California law requires that a lawsuit be filed to foreclose on a mechanic=s lien within 90 days (Civil Code section 3144) after recording it. If the contractor fails to file a lawsuit to foreclose on that lien within 90 days, it is barred from recovering on that stale mechanic's lien. If that happens, the question is what the contractor can do to try re-obtaining its mechanic's lien rights and, alternatively, what can the landowner do to have the stale lien removed. This article will discuss each party's legal rights when there is a stale lien.
The Rights of the Landowner
If a timely lawsuit is not filed, and the claimant refuses to release the lien or cannot be located, the property owner can file a petition, under Civil Code section 3154, to have the court remove the lien. That section basically states that at any time after the expiration of the 90 day period and where no action has been brought to enforce that lien, the owner of the property or the owner of any interest therein may petition the proper court for a decree to release the property from the lien. Such a petition is filed in the Superior Court in the county where the property is located. A hearing is then set not more than 30 days after the filing of the petition and the person seeking to have the lien removed must serve the petition and a notice of the hearing on the lien holder at least ten days before the hearing. Service can be made by registered or certified mail, with service effective five days after deposit. If the lien claimant responds to the petition, the response is limited to the timeliness of filing an action to foreclose on the lien. Neither party can raise any other claims or cross-claims in the proceeding. The prevailing party on the petition is entitled to attorneys' fees not to exceed two thousand dollars ($2,000).
It should be noted that filing a petition under section 3154 does not bar any other claim for relief by the owner of the property, and that the decree canceling a claimant's lien does not bar the lien claimant from bringing any other cause of action or claim for relief, other than an action foreclosing the lien.
The Rights of Lien Holder
Generally, a lien claimant can record a second lien if the first lien was voluntarily removed and the time for recording a second lien has not expired.
In the case of Koudmani v. Ogle Enterprises, Inc. (1996) 47 Cal App 4th 1650 a subcon??trac??tor filed a lien 87 days after the owner recorded a notice of completion. Fifteen days later, the subcontractor filed a second mechanic's lien. Two days after that, the owner's attorney sent a letter to the subcon??tractor, demanding that the original lien be released because the contractor had failed to file a fore??closure action on the first lien within 90 days of recording it. The subcontractor released the first lien, and then filed a timely foreclosure action on the second one. At that point, the owner filed a petition to release the lien, pursuant to Civil Code section 3154, which allows an owner to move the court to release a lien when a foreclosure action has not been filed within 90 days of the recording of the lien. The trial court ruled against the subcontractor, and released the property from the second lien. The appellate court reversed the trial court's decision and allowed the subcontractor to foreclose on his second lien. Civil Code section 3154 provides owners with a simple remedy to remove mechanic's liens when lien claimants fail to file timely actions to foreclose on them. However, if a claimant voluntarily releases a lien before the owner files a petition, the release does not, on its face, bar the claimant from filing a second timely lien.
If a contractor has failed to file a timely foreclosure lawsuit, a contractor should determine if he or she can record a second mechanic's lien in a timely manner. The specific time limitation for recording a lien is based on: (a) whether actual completion is obtained or there is an equivalent to completion obtained; (b) whether or not the owner shortened the deadlines by recording a Notice of Completion or Notice of Cessation; and (c) whether or not the contractor has a direct contract with the owner of the project.
The general rule is when all the work on the project has actually been completed all possible lien claimants must record their liens within ninety (90) days from the date of actual completion. (Civil Code ???? 3115, 3116). Even if the project is not complete, if there is a cessation of labor for a continuous period of sixty (60) days California law declares that such cessation is deemed an equivalent to the completion of the work. After that sixty day period elapses, all possible lien claimants must record their liens within ninety (90) days from that date. A project is also deemed complete when (1) the owner occupies or uses the property and all work stops; (2) the owner accepts the work; or (3) work ceases for a continuous period of thirty (30) days and the owner records a notice of cessation. (Civil Code ?? 3086)
California law allows an owner to record one of two types of possible notices that, after timely recordation, will shorten the time for recording a mechanic's lien. The two types of notices are either a Notice of Completion or alternatively a Notice of Cessation. By shortening the time within which to record Liens and serve Stop Notices, the Notice of Completion and/or Cessation can be very useful from an owner's or lender's perspective, and from the Lien and Stop Notice claimant's perspective, a fatal trap if the shortened time limits are not met.
A Notice of Cessation is used when work has temporarily halted for more than 30 days. (Civil Code ??3092). A Notice of Completion must be filed after work has actually been completed, as that term is defined in Civil Code ??3086. Listing an erroneous date of completion does not affect the validity of the notice so long as the true date of completion was within 10 days preceding the date of recording of such notice.
The deadlines if a Notice of Completion or a Notice of Cessation are:
i. For a Notice of Completion:
When the owner records a valid Notice of Completion (i.e., a proper Notice of Completion recorded within ten days after actual completion of work on the project). (Civil Code ??3093).
???(1) A prime contractor in direct contract with the owner must record his lien within sixty (60) days of the recording of the Notice of Completion. (Civil Code ?? 3116).
???(2) All others must record their liens within thirty (30) days of the date the Notice of Completion is recorded. (Civil Code ?? 3116).
ii. For a Notice of Cessation:
(1) If the owner, after a thirty (30) day continuous cessation of labor, records a Notice of Cessation, this is equivalent to the recording of a Notice of Completion. (Civil Code ?? 3092).
(2) In that case, the prime contractor has sixty (60) days, and all other claimants have thirty(30) days, within which to record their liens. (Civil Code ???? 3115, 3116).
Trivial work performed after completion or after a notice is recorded will not invalidate it. Within ten days after the owner records a Notice of Completion or a Notice of Cessation, the Owner must give notice to the prime contractor and to any subcontractor or supplier who served a preliminary notice on the Owner. (Civil Code ?? 3259.5) If the Owner fails to do so, the notice is ineffective. However, "owner" for purposes of section 3259.5 does not include lenders or anyone who uses the building as a personal residence so long as there are no more than four units in the building. Co
In conclusion, if a contractor has failed to file a timely foreclosure lawsuit, a contractor should determine if he or she can record a second mechanic's lien in a timely manner (e.g., 30, 60, or 90 days after the project is substantially completed). If so, the first lien should be released the first lien and a new one recorded. However, the lien release should clearly indicate that the original claim remains unsatisfied. Conversely, if the lien has been satisfied the lien release should expressly state that the underlying obligation has been fully satisfied. If the lien release is not clear as to what is being released, the owner may then argue that the contractor has released all its rights to record a new lien.
This article, ??2010 was written by William C. Last, Jr. Mr. Last is an attorney who has been specializing in Construction Law for over 30 years. In addition to belonging to a number of construction trade associations, Mr. Last holds a California "A" and "B" license. He can be contacted at 415-764-1990 or 650-425-4679. A number of his past articles can be found on his website (lhfconstructlaw.com). This bulletin is published periodically to provide general information about current legal issues. The articles are not intended to be a substitute for the advice of an attorney as to a specific problem. If you have a specific legal question or need legal advice, you should contact an attorney.
Beginning in January 2011 Mechanic's Lien Claimants will be Required to Serve Project Owners a Specified Notice Before Recording Their Lien
Posted by: Jonathan Bowne
November 02, 2010
At present, to record a mechanic's lien a claimant need only to complete and execute a claim of lien form and record the same at the county recorder's office in the county where the project was located. The claimant has no obligation to inform the project owner that the lien has been recorded. Occasionally project owners first learn that their property is subject to a mechanic's lien when they are served an already filed lawsuit seeking foreclosure of the lien.
Even when project owners are informed that a mechanic's lien has been recorded, they may not understand the nature of a mechanic's lien and how it can threaten their interest in the subject property.
Both of these scenarios can prohibit an early, informal resolution of the dispute, which is often detrimental to both parties, and - needless to say - the over crowded civil courts.
Modifications to Civil Code section 3084 which will go into effect on January 1, 2011 will seek to ensure that project owners are informed immediately that a mechanic's lien has been recorded and provide them with basic information about the nature and possible impacts of the lien.
When the modifications go into effect claimants will be required - before they record their claim of lien - to, 1) include in their lien document a specified notice which is set forth in Section 3084(a)(7); and 2) mail the lien document to the project owner via registered, certified, or first-class mail and include with their lien document a proof of service affidavit.
The specified notice includes basic information regarding mechanic's liens, including the fact that the liened property may be subject to a lawsuit seeking a foreclosure sale. The proof of service affidavit is to be recorded along with the claim of lien.
The modified version of the statute specifically provides that the failure to serve the lien document and specified notice as provided therein shall invalidate the said lien.
Most contractors use "fill in the blank" forms to draft mechanic's liens. Presumably the publishers of these forms will modify their documents to conform to the new requirements. Contractors will just need to ensure that come January 2011 they are using an updated form.
Beginning in January 2011 a Lis Pendens Will Become a Mandatory Element to Enforcing a Mechanic's Lien
Posted by: Jonathan Bowne
November 01, 2010
A lis pendens (a.k.a. notice of pendency of action) is a document which is recorded against the title of real property to notify interested parties that litigation is pending which impacts the said property's title. The lis pendens protects claimants by ensuring that their claim is fully attached to the property and that future interest holders take title subject to the claim, and protects future interest holders by warning them that the claim exists.
While it is common to record a lis pendens relative to a mechanic's lien claim, doing so is currently not required. But on January 1, 2011 Civil Code section 3146 will be amended to make the recording of a lis pendens a mandatory element of enforcing a mechanic's lien. Claimants will be required to record a lis pendens on or before 20 days after the filing of a mechanic's lien foreclosure action.
While the new version of the statute does not explicitly state as such, its wording makes it clear that the failure to record the lis pendens will invalidate a mechanic's lien claim. As such, to the extent they were not doing so already, mechanic's lien claimants and their attorneys should add the recordation of a lis pendens to the check list of required steps to perfecting a lien.
Click here to see the full language of the modified version of the statute.
Topics
2008 Annual California Construction Law Update
A 2010 UPDATE ON NEW CALIFORNIA LAWS THAT IMPACT THE CONSTRUCTION INDUSTRY
Bidding, Mistaken Bids, Withdrawal of Bids, Bid Bond Claims and Bid Disputes
California Contractor License Law
Claims on Public Works Projects
Construction Environmental Issues
Contract Interpretation
Employer/Employee
Green Building
Insurance and Indemnity
Legislative Developments
Mechanics Liens, Stop Notices and Payment Bonds
New California Construction Related Laws That Become Effective During 2009
Public Works Contracting-Liquidated damages
Regulations Impacting Construction
Subcontract Liablity
Recent Updates
January 17, 2012
A 2012 Update on New California Laws that May Impact the Construction Industry
January 06, 2012
Can a project owner sue a contractor for slander of title on the basis that the contractor's mechanic's lien lacks merit? The answer is no.
January 03, 2012
Are you Prequalified to be Awarded Small Public Projects not Subject to Formal Bidding Requirements?
November 03, 2011
Class A (General Engineering) licensed subcontractor deemed duly licensed even though the contract required C-12 license (Earthwork and Paving)

